The Vista Irrigation District board voted unanimously, 5-0, to approve a resolution opposing San Diego Gas & Electric's proposed Golden Pacific Powerlink as proposed at a special meeting Wednesday, Oct. 14, General Manager Brett Hodgkiss told The Golden Coast Journal in an email that day. The board did not give direction on preferred alternative routes, he said. All of SDG&E's preliminary routes for the 500-kilovolt transmission line, preferred and alternative, would cross land the district owns in Warner Springs, according to the staff report in the meeting's agenda packet.

Staff had recommended that the board consider adopting a resolution opposing the project "as proposed" and/or give staff direction on any aspect of it, according to the report, which was prepared by Director of Water Resources Lesley Dobalian and approved by General Manager Brett Hodgkiss. The draft resolution says the district "strongly opposes the project as currently proposed" and calls on SDG&E and the California Public Utilities Commission to work with the district to identify alternative alignments that would avoid or mitigate the harm. Staff had also asked the board for direction on any district-preferred alternative routes. The board approved the resolution but did not give that direction, Hodgkiss said.

A map attached to the staff report estimates how far the routes would run across the district's Warner Ranch. It labels SDG&E's preferred route study corridor at about 14 miles on district land, the South Mountain alternative at about 6 miles and the Montezuma Grade alternative at about 4 miles. The map notes that the distances are measured only within the district boundary and that the line locations are approximate. Hodgkiss pointed The Golden Coast Journal to the map in an Oct. 8 email. According to the staff report, the towers would stand just under 200 feet tall and SDG&E would need an easement 200 to 250 feet wide.

The district serves more than 135,000 people in Vista and parts of San Marcos, Escondido, Oceanside and unincorporated San Diego County. It owns Lake Henshaw, Henshaw Dam and the surrounding 43,000 acres over the Warner Valley Groundwater Basin, known as Warner Ranch, and typically gets 15 to 25 percent of its water from the lake, according to an Aug. 17 letter from General Manager Brett Hodgkiss to Supervisor . Water released from Lake Henshaw also supplies the City of Escondido and five federally recognized tribes, the La Jolla, Pauma, Rincon, Pala and San Pasqual bands.

In the letter, Hodgkiss wrote that construction could alter hydrologic flows, degrade water quality and introduce contaminants into the lake, and that permanent transmission infrastructure poses long-term risks to water production and quality. He noted that several faults, including the Elsinore Fault Zone, cross the Warner Basin.

The district also pointed to firefighting. Cal Fire relied on the district's groundwater wells and Lake Henshaw water to fight the Grade Fire, which began July 31 on property next to district land, helping hold it to about 700 acres, the letter says. "A transmission-line related wildfire, or an incident that damages or limits access to the District's groundwater wells or Lake Henshaw when the immediate demand for those resources is greatest could have devastating impacts to the District's water supply as well as to the local community," Hodgkiss wrote.

The staff report says the line could also undercut the district's plans to rely more on Warner Basin groundwater. After studying whether to replace or retire the 100-year-old, 11-mile Vista Flume, the district decided to replace it and maximize local groundwater production, and it is spending more than $18 million on environmental, engineering and design work for the replacement. The project could also affect the district's Warner Ranch agreements for cattle grazing, recreation, wireless telecommunications, Cal Fire and the U.S. Navy's Remote Training Site Warner Springs, the report says, and the draft resolution warns that lost lease revenue could force higher water rates. SDG&E has already asked for access to district land for land, biological and cultural surveys. The report lists the fiscal impact as unknown.

Opposition surfaced at the board's Sept. 9 meeting, according to draft minutes. Bob Garcia of the Save Warner Springs Organization said his group strongly opposes the project and asked the board to delay any decisions on property negotiations with SDG&E; President Marty Miller said the board would not make decisions in closed session. Three residents of Warner Valley, Palomar Mountain and Warner Springs also urged the board to oppose the line. The board then met in closed session on potential real property transactions involving four Warner Ranch parcels, with SDG&E listed as the negotiating party. Afterward it reported no action but directed staff to schedule the Oct. 14 meeting. Director Patrick Sanchez said Desmond would hold an open house on the project Oct. 13 and 14.

The packet also includes letters urging opposition. One came from Save Our Heritage Organisation, which operates the district-owned Warner-Carrillo Ranch House, a National Historic Landmark. Another came jointly from the Anza-Borrego Foundation and The Chaparral Lands Conservancy, which say proposed routes would also cut through Anza-Borrego Desert State Park. District staff met with SDG&E on July 28, and the utility has offered to present the project to the board at a future meeting, the staff report says.

SDG&E says the California Independent System Operator identified the need for the line, which would run from the utility's Imperial Valley Substation to a new substation in southern Orange County at an estimated cost of about $1.6 billion. The utility's timeline calls for a California Public Utilities Commission filing in fall or winter 2026, permitting from 2026 to 2029, construction starting in fall 2029 and service in 2032. The CPUC will select the final route, according to the project website. The staff report says the grid operator included the project in its 2022-2023 Transmission Plan as one of 45 recommended projects, and that formal environmental review under the California Environmental Quality Act will begin after SDG&E files a complete application.

Before the 1 p.m. meeting at the district's headquarters, 1391 Engineer St. in Vista, the public could comment in person, by phone or by email, according to the agenda.

Local

Jim Desmond

Supervisor, Fifth District, San Diego County Board of Supervisors

Named 2 times in this story.

Portrait: County of San Diego / Wikimedia Commons (Public domain)

Sources & methodology

This report was written from the primary materials below. Links open at the original publisher.

Vista Irrigation District, board to consider opposing Golden Pacific Powerlink project (October 2026) Vista Irrigation District letter to Supervisor Jim Desmond (Aug. 17, 2026) Vista Irrigation District Sept. 23, 2026 board packet (draft Sept. 9 minutes) SDG&E Golden Pacific Powerlink project website Vista Irrigation District Oct. 14, 2026 special meeting agenda packet (staff report, draft resolution and route map)

See something we should correct? Read our corrections policy.